Quarterly Activities Report Update
Released
Released
Announcement PDF
ASX Release
Report for the Quarter Update
Ended 30 September 2015
16 October 2015
ASX Code: DTM
Key Projects:
Unicorn Porphyry: Mo-Cu-Ag
Copper Quarry: Cu-Au
Gentle Annie: Cu
Morgan Porphyry: Mo-Ag-Au
Fairley’s: Au
Mountain View: Au
Investment Data: Shares on
issue: 243,257,892 Unlisted
options: 15,473,048
Substantial Shareholders:
Top 20 Holdings: 51.13%
Corporate Update
A review of the Company’s direction and strategy was implemented over the
course of the period.
Further study around the immediate viability of the Mt Unicorn Mo-Cu-Ag project
was undertaken and completed.
Conclusions drawn from the Mt Unicorn project study indicate that for the time
being economic risks around further work and development are too great to
proceed with any substantial expenditure and development at this time.
The board continues to seek potential joint venture partners for the Mt Unicorn
project which may materialize over time as and when a recovery in the Mo price
is seen as sustainable.
The board adopted a recommendation to pursue the acquisition and
development of more Au projects that fit predetermined criteria. These criteria
are limited by Geographic location, Project size (large and small), as well as
Financial capacity to execute such ventures.
Development work on Mt View progressed as the company seeks to bring the
project into production.
Board & Management:
Managing Director: James Chirnside
Non-Executive Director: Luke Robinson
Non-Executive Director: Russell Simpson
Company Secretary: Julie Edwards
Dart Mining NL
ACN 119 904 880
Contact Details:
4 Bryant Street, Corryong VIC 3707 Australia
James Chirnside
Phone: +61 (0)498 732 742
Email: jchirnside@dartmining.com.au
Visit our webpage: www.dartmining.com.au
On-going Au opportunities and negotiations are the Company’s primary focus
for the immediate future.
At the end of the quarter the Company’s cash position stood at approximately
$683,000.
Unicorn Project – Study Update
The key findings and assumptions around the 27 May ASX Announcement
concerning the Unicorn Project are being documented in a detailed report by
Metallurgist Colin Seaborn. This report will pull together the findings and extensive
test work conducted as part of the ongoing study since May 2014. The study was
commissioned by the Board to clarify the level of accuracy for each aspect of the
various studies undertaken as input into the 27 May ASX release. The market has
previously been informed (latest as of 26 September 2014 in the company Annual
Report) that a Prefeasibility Study (PFS) would be completed for the Unicorn
Project by June 2015 – being part of the $9.9M Strategic Plan (ASX release 24
March 2014). A PFS is generally accepted as having a +/- 25% level of accuracy
for the input data, this allows economic assessments to be made of projects within
this level of confidence. The previous reporting around the confidence level
(accuracy) of the various studies has been confusing, firstly being referred to as an
industry standard PFS (Prefeasibility Study) in the March 24 2014 ASX release,
then as a Project Study in the 2015 March 31 Quarterly Report and finally as a
Project Definition Study (PDS) in the 27 May release. The Unicorn Project PFS
Update report seeks to identify where each key aspect of the project is with
respect to the desired PFS level of accuracy.
GOLD ASSET DEVELOPMENT UPDATE
Following the appointment of a new Board at the general meeting (18 June 2015), the main focus of
exploration has been on further work around the known gold prospects within the tenement package.
The approved Mountain View Mining Licence (ML5559) and gold mineralisation identified at the Onslow
Reefs and Fairley’s prospects have been further reviewed with the aim of assessing the viability of each
prospect for gold production (Figure 1).
Figure 1. Key Prospect Location Plan.
2
MOUNTAIN VIEW PROJECT
Scoping level mine design and costing aspects of the proposed Mountain View open pit have been
completed with bulk sampling now necessary to complete detailed metallurgical studies. A work plan
has been submitted to carry out the bulk sampling program, with approvals expected early in the next
quarter. The bulk sampling will provide recovery details and indicate the best toll treatment facility for the
ore style, this will also allow negotiations to be finalized on treatment costs and allow completion of a
preliminary economic assessment of the Mountain View mineralisation.
A program of targeted infill soil geochemistry using a portable XRF (pXRF) has recently been completed.
The infill soil traverses test a 1.2km long area to the north of the previously conducted Mountain View
gold soil grid (Figure 2). The results have been very encouraging, confirming previous board scale soil
geochemistry lines that showed anomalous gold and arsenic in soils around the historic workings of the
New Discovery mine, some 1.3km north of the Mountain View mine. The recent infill soil survey has now
identified four arsenic in soil anomalies up to 350m in length from insitu B horizon soil sampling, the soil
traverses are spaced at 20m along the strike of mineralisation and each sample is collected at 5m
intervals across strike (Figure 2). This soil survey highlights the likely repetition of gold mineralised
sulphide lenses; the most northern arsenic anomaly (350m in length) corresponds with the historic New
Discovery lens. Previous rock chip sampling (See ASX DTM 12 March 2009) has shown up to 1.5m @
5.38 g/t Au within the historic workings. The potential for the repetition of mineralised pods along the
strike of the Brown’s Creek fault had already been established to the south of the Mountain View mine
with further historic workings located at the South Golden Bell, also showing corresponding elevated
arsenic in soil. Discreet arsenic in soil anomalies along the Mountain View line are now evident over
some 2 km of strike length with six zones currently identified that are worthy of first pass shallow drilling.
FAIRLEY’S PROJECT
A mineralisation Report is currently being prepared for the Fairley’s Project using all available drill and
rock chip data to model the currently tested near surface mineralisation. The mineralisation report will
accompany an application for the renewal of the Buckland EL4724 (Figure 1). The completed pXRF soil
sample traverses at Fairley’s have highlighted the growing scope of the system to host multiple
outcropping mineralised zones over the completed 800m of the survey grid (Figure 3) as well as the
deeper potential already identified in the previous diamond drilling. The two additional soil traverses at
the far south of the grid have again shown some very exciting results with highly anomalous soil arsenic
levels up to 450m in width, the highest arsenic in soil levels within this southern zone may correspond
with a new Central Shear (identified during early exploration mapping) and the strike extension of the
western lines toward the western end of the traverses. The new central zone and the previously
identified anomalies clearly warrant drill testing and require the preparation of a new work plan for drilling
and drill access track construction. The mineralisation report and EL4724 (Buckland) renewal application
will be the focus of the next Quarter, with additional soil traverses and work plan preparation for further
drilling planned for the March 2016 Quarter.
ONSLOW REEFS PROSPECT
A small program of RC drilling that was scheduled for the September Quarter at the Onslow Reefs was
deferred pending the outcome of detailed metallurgical test work on the Mountain View mineralisation
and completion of the scoping level economic viability study. Outcomes of the Mountain View study are
likely to be directly applicable to the Onslow Reefs system with a similar silica / sulphide mineralisation
style.
3
Figure 2. Infill pXRF Soil As geochemistry colour contour over previous gold soil results – north of Mountain View pit and
approved Mining Licence ML5559. Plan also shows previous rock chip and grab sampling at the New Discovery Mine.
4
Figure 3. pXRF Soil As geochemistry colour contour over topography showing the location of historic workings and
various parallel and strike extensions of mineralised shear systems at Fairley’s Project – Buckland EL4724.
Tenement Status Report as at September 30 2015
Renewal applications for EL4724 (Buckland) and EL4726 (Dart) are being prepared for submission early in the next Quarter.
The majority of the key projects are located inside these two tenements with ongoing exploration planned ahead of further
resource estimation and subsequent application for either additional mining licenses (ML) or retention licenses (RL).
Tenement Number
EL4724
EL4726
EL5058
EL5194
EL5467
EL5468
ML5559
Name
Buckland2
Dart1&2
Cudgewa
Mt. Alfred
Mcormacks
Upper Murray
Mt View
Area (Grats)
82
680
413
51
92
198
4.8
Interest
100%
100%
100%
100%
100%
100%
100%
Location
NE Victoria
NE Victoria
NE Victoria
NE Victoria
NE Victoria
NE Victoria
NE Victoria
All tenements remain in good standing at 30 September 2015.
NOTE 1: Unicorn Project area subject to a 2% NSR Royalty agreement with BCKP Limited (Orion Mine Finance) dated 29 April
2013.
NOTE 2: Areas subject to a 1.5% Founders NSR Royalty Agreement
5
Competent Persons Statement
The information in this report that relates to Exploration Results is based on information compiled by
Dean Turnbull B.App.Sc.(Geol) Hons. M. AIG, a Competent Person who is a Member of the Australian
Institute of Geoscientists. Mr Turnbull is a full time employee of Dart Mining NL. Mr Turnbull has
sufficient experience that is relevant to the style of mineralisation and type of deposits under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the
2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves”. Mr Turnbull consents to the inclusion in the report of the matters based on his information in
the form and context in which it appears.
JORC CODE, 2012 EDITION – TABLE 1
SECTION 1 SAMPLING TECHNIQUES AND DATA
Criteria
Sampling
techniques
JORC Code explanation
Commentary
Nature and quality of sampling (e.g. cut channels,
random chips, or specific specialised industry standard
measurement tools appropriate to the minerals under
investigation, such as down hole gamma sondes, or
handheld XRF instruments, etc.). These examples
should not be taken as limiting the broad meaning of
sampling.
Include reference to measures taken to ensure sample
representivity and the appropriate calibration of any
measurement tools or systems used.
Aspects of the determination of mineralisation that are
Material to the Public Report.
In cases where ‘industry standard’ work has been done
this would be relatively simple (e.g. ‘reverse circulation
drilling was used to obtain 1 m samples from which 3
kg was pulverised to produce a 30 g charge for fire
assay’). In other cases more explanation may be
required, such as where there is coarse gold that has
inherent sampling problems. Unusual commodities or
mineralisation types (e.g. submarine nodules) may
warrant disclosure of detailed information.
Hand held XRF (pXRF)
analysis is performed on the
samples from the top of the
clay layer (B-Horizon) without
pulverization.
XRF calibration is examined
using duplicate samples
submitted for commercial
assay analysis and the
equivalent XRF sample data
compared where possible.
Assay standards are also
included in sampling programs
to establish accuracy. Sample
representivity is examined by
comparison of adjacent
samples – data is reviewed
during interpretation where
geochemical results are
compared against the
geological setting, previous
results and standard reference
material values.
Chip sampling (where
reported) is carried out along a
marked line, perpendicular to
the strike of the mineralisation,
as a series of closely spaced
rock chips within a 50 –
100mm halo to the sample
line. Samples are generally 2
– 3 kg in size, the samples are
shipped to the laboratory,
dried, crushed and whole
sample pulverised prior to riffle
splitting for assay.
Drilling
techniques
Drill type (e.g. core, reverse circulation, open-hole
hammer, rotary air blast, auger, Bangka, sonic, etc.)
and details (e.g. core diameter, triple or standard tube,
depth of diamond tails, face-sampling bit or other type,
whether core is oriented and if so, by what method,
etc.).
NA
6
Criteria
Drill sample
recovery
Logging
Sub-sampling
techniques
and sample
preparation
Quality of
assay data
and
laboratory
tests
Verification
of sampling
and assaying
JORC Code explanation
Commentary
Method of recording and assessing core and chip
sample recoveries and results assessed.
Measures taken to maximise sample recovery and
ensure representative nature of the samples.
Whether a relationship exists between sample recovery
and grade and whether sample bias may have occurred
due to preferential loss/gain of fine/coarse material.
Whether core and chip samples have been geologically
and geotechnically logged to a level of detail to support
appropriate Mineral Resource estimation, mining
studies and metallurgical studies.
Whether logging is qualitative or quantitative in nature.
Core (or costean, channel, etc.) photography.
The total length and percentage of the relevant
intersections logged.
If core, whether cut or sawn and whether quarter, half
or all core taken.
If non-core, whether riffled, tube sampled, rotary split,
etc. and whether sampled wet or dry.
For all sample types, the nature, quality and
appropriateness of the sample preparation technique.
Quality control procedures adopted for all sub-sampling
stages to maximise representivity of samples.
Measures taken to ensure that the sampling is
representative of the in situ material collected, including
for instance results for field duplicate/second-half
sampling.
Whether sample sizes are appropriate to the grain size
of the material being sampled.
The nature, quality and appropriateness of the assaying
and laboratory procedures used and whether the
technique is considered partial or total.
For geophysical tools, spectrometers, handheld XRF
instruments, etc., the parameters used in determining
the analysis including instrument make and model,
reading times, calibrations factors applied and their
derivation, etc.
Nature of quality control procedures adopted (e.g.
standards, blanks, duplicates, external laboratory
checks) and whether acceptable levels of accuracy (i.e.
lack of bias) and precision have been established.
The verification of significant intersections by either
independent or alternative company personnel.
The use of twinned holes.
Documentation of primary data, data entry procedures,
data verification, data storage (physical and electronic)
protocols.
Discuss any adjustment to assay data.
NA
NA
NA
Soil gold levels (where
determined) use ALS
technique Au-AA22, which is
a low detection limit
(0.001ppm) technique
commonly used in
geochemical investigations.
Verification of significant
intersections were made by
alternative company
personnel.
Data were logged onto paper
and transferred to a
spreadsheet and checked
Electronic only assay data is
imported into a spreadsheet
from the laboratory’s electronic
data or the pXRF unit.
7
Criteria
Location of
data points
JORC Code explanation
Commentary
Accuracy and quality of surveys used to locate drill
holes (collar and down-hole surveys), trenches, mine
workings and other locations used in Mineral Resource
estimation.
Specification of the grid system used.
Quality and adequacy of topographic control.
Hand held GPS locations mark
the start and end of each soil
line, soil sample locations are
then either located by GPS or
measured offsets along soil
lines by tape and compass
(corrected for slope) –
Absolute location accuracy is
+/- 10 – 15m.
All maps, plans and data are
on an MGA datum and GDA94
zone 55 projection.
Elevation is established from
government 10 and 20m
contour mapping.
Data spacing
and
distribution
Data spacing for reporting of Exploration Results.
Whether the data spacing and distribution is sufficient
to establish the degree of geological and grade
continuity appropriate for the Mineral Resource and Ore
Reserve estimation procedure(s) and classifications
applied.
Whether sample compositing has been applied.
Whether the orientation of sampling achieves unbiased
sampling of possible structures and the extent to which
this is known, considering the deposit type.
If the relationship between the drilling orientation and
the orientation of key mineralised structures is
considered to have introduced a sampling bias, this
should be assessed and reported if material.
The measures taken to ensure sample security.
Soil data spacing varies across
prospects and different
mineralisation styles – spacing
is based on expected
continuity of mineralisation, no
data compositing or
manipulation is carried out.
Soil sampling lines are,
wherever possible, oriented as
close to perpendicular as
possible to the expected strike
of mineralisation.
Orientation of
data in
relation to
geological
structure
Sample
security
Audits or
reviews
The results of any audits or reviews of sampling
techniques and data.
All samples submitted for
commercial assay analysis are
placed in sealed polyweave
bags and delivered to a
commercial transport company
for delivery to the laboratory.
Any evidence of sample
damage or tampering is
immediately reported by the
laboratory to the company and
a decision made as to the
integrity of the sample and the
remaining samples within the
damaged / tampered bag/s.
An internal review of
procedures, operations,
sampling techniques and
analytical techniques was
made by Dart Mining.
8
SECTION 2 REPORTING OF EXPLORATION RESULTS
Criteria
Mineral
tenement and
land tenure
status
JORC Code explanation
Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint
ventures, partnerships, overriding royalties,
native title interests, historical sites,
wilderness or national park and environmental
settings.
The security of the tenure held at the time of
reporting along with any known impediments
to obtaining a licence to operate in the area.
Exploration
done by other
parties
Acknowledgment and appraisal of exploration
by other parties.
Geology
Deposit type, geological setting and style of
mineralisation.
Drill hole
Information
A summary of all information material to the
understanding of the exploration results
including a tabulation of the following
information for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level –
elevation above sea level in metres) of the
drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
If the exclusion of this information is justified
on the basis that the information is not
Material and this exclusion does not detract
from the understanding of the report, the
Competent Person should clearly explain why
this is the case.
Commentary
Tenement
Number
Name
Area
(Grats)
EL4724
Interest
Location
Buckland2
82
100%
NE Victoria
EL4726*
Dart1&2
680
100%
NE Victoria
EL5058
Cudgewa
413
100%
NE Victoria
EL5194
Mt. Alfred
51
100%
NE Victoria
EL5467
Mcormacks
92
100%
NE Victoria
EL5468
Upper Murray
198
100%
NE Victoria
MIN5559
Mt View
4.8
100
NE Victoria
Renewal applications for EL4724 (Buckland) and
EL4726 (Dart) are being prepared for submission early
in the next Quarter.
All tenements remain in good standing at 30
September 2015. NOTE 1: Unicorn Project area subject
to a 2% NSR Royalty agreement with BCKP Limited
(Orion Mine Finance) dated 29 April 2013. NOTE 2:
Areas subject to a 1.5% Founders NSR Royalty
Agreement
No reported soil surveys have been
conducted at the Fairley’s Project by
previous explorers. Very limited broad
scale soil lines were carried out at the
Mountain View Project area by
Tanganyika Holdings and Border Gold –
sample density was not adequate to
assist in the detailed understanding of
shoot scale sulphide lens distribution.
Fairley’s is an orogenic fault-hosted gold
system consisting of mineralisation
associated with silicification and clay
alteration with fine disseminated sulphide.
The disseminated gold mineralisation is
associated with fine arsenopyrite within
sheared sediments.
Mountain View mineralisation is fault
hosted and consists of a silica sulphide
alteration with associated fine gold.
Mineralisation occurs within dilatation
sites along the Browns Creek fault within
the Wabisco Shale.
NA
9
In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (e.g. cutting of
high grades) and cut-off grades are usually
Material and should be stated.
Where aggregate intercepts incorporate short
lengths of high grade results and longer
lengths of low grade results, the procedure
used for such aggregation should be stated
and some typical examples of such
aggregations should be shown in detail.
The assumptions used for any reporting of
metal equivalent values should be clearly
stated.
These relationships are particularly important
Relationship
in the reporting of Exploration Results.
between
If the geometry of the mineralisation with
mineralisation
respect to the drill hole angle is known, its
widths and
nature should be reported.
intercept
If it is not known and only the down hole
lengths
lengths are reported, there should be a clear
statement to this effect (e.g. ‘down hole
length, true width not known’).
Appropriate maps and sections (with scales)
Diagrams
and tabulations of intercepts should be
included for any significant discovery being
reported These should include, but not be
limited to a plan view of drill hole collar
locations and appropriate sectional views.
Where comprehensive reporting of all
Balanced
Exploration Results is not practicable,
reporting
representative reporting of both low and high
grades and/or widths should be practiced to
avoid misleading reporting of Exploration
Results.
Other exploration data, if meaningful and
Other
material, should be reported including (but not
substantive
limited to): geological observations;
exploration
geophysical survey results; geochemical
data
survey results; bulk samples – size and
method of treatment; metallurgical test
results; bulk density, groundwater,
geotechnical and rock characteristics;
potential deleterious or contaminating
substances.
Further work The nature and scale of planned further work
(e.g. tests for lateral extensions or depth
extensions or large-scale step-out drilling).
Diagrams clearly highlighting the areas of
possible extensions, including the main
geological interpretations and future drilling
areas, provided this information is not
commercially sensitive.
Data
aggregation
methods
NA
NA
NA
All significant / relevant precious or
pathfinder elements are reported with
either assay value in full or presented to
display the full range of assay data
returned.
Any other relevant information is
discussed in the main body of the report.
Planned work is discussed in the body of
the report and is dependent on future
company direction.
10
Share your feedback
Discover