TRIUMPH GOLD PROJECT DRILLING PROGRESS UPDATE
Dart Mining NL (“Dart” or the “Company”) is pleased to release an update of the Triumph Gold project
drilling programme. Dart has been drilling in and around the Inferred Mineral Resource area with
the Company’s diamond drill rig to acquire important structural orientation and confirmation assay
data across various sites. The next phase of drilling is to include exploratory deep holes.
HIGHLIGHTS
•
Dart has completed 1,637m (10 holes) of diamond core drilling across the New Constitution and
South Constitution (assays pending) of its initial 7,000m planned programme;
•
Nine new zones of sulphide mineralisation have been interpreted from the drill holes to date;
the company is continuing interpretation from logging and is eagerly awaiting assay results from
the first 10 holes, expected to be available for release towards the end of June.
•
Most notable are the strong zones of alteration, veining, and logged sulphide mineralisation
that have been intersected to the east of New Constitution (TRDD006 – See Figure 3 for core
photos). This includes sampled zones of up to ~15% estimate of arsenopyrite among other
sulphides (pyrite and sphalerite);
•
Dart continues to drill test structural and step out concept targets to extend and improve the
Mineral Resource Estimate at Triumph; and
•
Dart has now established a good drilling rhythm with balanced back-to-back drill crews,
operational awareness of the Triumph ground, and improvements in operation logistics
planning. A peak shift record of 48.0m diamond drilled was achieved on the 28th May 2025.
Visual estimates of mineralisation presence and abundance contained in this announcement
should never be considered a proxy or substitute for Laboratory analysis. Visual estimates
potentially provide no information regarding concentration of economic grades or factors,
impurities or deleterious physical properties relevant to valuation.
The work to date has highlighted potential for further expanding and updating the existing known
Inferred Mineral Resource Estimate thereby unlocking an expanded potential of the Triumph
system. Key structural controls have been confirmed through diamond drilling, with additional
sulphide mineralisation observed outside the mineral resource in all holes. Strong geological
controls on mineralisation are now understood with key mineral systems models tested leading to
additional targeting work looking to unlock the sites potential.
Dart Mining NL
ABN: 84 119 904 880
Level 6, 412 Collins Street
Melbourne VIC 3000
Contact: James Chirnside
Email: jchirnside@dartmining.com.au
Mobile: +61 447 447 613
Webpage: www.dartmining.com.au
LinkedIn: Dart Mining NL
Twitter: @DartMining
1|Page
Dart has seen great improvements in the average metres drilled per day since January 2025, despite
increases in total rainfall in the Gladstone region, peaking in April (Figure 1). As the drill crews settle
in and learn more of the ground, logistics such as earthworks become more accessible, and we
continue to finalise camp and laydown areas, more improvements in the average metres per shift
are anticipated.
Triumph Diamond Drilling Performance
Average Metres Per Day
Dart Average Metres Per Shift
Gladstone Rainfall (mm total)
25
250
20
200
15
150
10
100
5
50
0
0
Jan
Feb
Mar
Apr
May
2025 Monthly Breakdown
Figure 1: Average metres per shift and total rainfall for the Gladstone area from January 2025 through 26th May 2025.
Figure 2: Diamond core drill site setup at New Constitution.
The first holes completed aimed to expand and upgrade the Inferred Mineral Resources of the two
key prospects within the project; New Constitution and South Constitution. Dart’s owned and
operated drill rig is producing critical diamond drilling samples for structural and mineralisation
interpretation. This new drilling will strongly enhance the RC dominant results database that
underpins the current Inferred Mineral Resource.
2|Page
The location of the drill holes completed to date is shown in Figure 3. An impressive advancement
in the knowledge of the deposits include intersected new zones of strong alteration and
mineralisation in each of the first 6 fully logged and sampled holes. These zones are both on the
eastern and western side of New Constitution, and north side of South Constitution.
Figure 3: Plan map showing location of drilling to date compared to the existing Inferred Mineral Resource Estimate.
TRDD006 is an example of additional zones that have been intersected that are not included in the
current Mineral Resource Estimate. TRDD006 intercepts (Figure 4) are extension areas of New
Constitution and suggests close proximity Mineral Resource growth adjacent to the existing Inferred
New Constitution Mineral Resource. This includes zones of 15% Asp by visual estimate as shown in
Figure 5. Figure 4 highlights a typical zone for Triumph where intense alteration (that includes the
mineralisation) is in stark contrast to the relatively un-altered host tonalite, suitable for in-pit ore
identification in an operating environment. Samples for drill holes have been cut and delivered for
laboratory analysis.
3|Page
Figure 4: TRDD006 129m - 143m extensive zone of strong alteration, logged sulphide mineralisation and structural zones as part of
Darts targets on expanding New Constitution to the east.1,2
Figure 5: TRDD006 113m - 116m strong zone of intense mineralisation crosscut by a post mineral dyke. Visual estimate of the
mineralised zone is 15% Asp.
1
Asp = arsenopyrite and Py = pyrite
2
Visual estimates of mineralisation presence and abundance contained in this announcement should never be considered a proxy or substitute for
Laboratory analysis. Visual estimates potentially provide no information regarding concentration of economic grades or factors, impurities or
deleterious physical properties relevant to valuation.
4|Page
In addition to these new mineralised zones the drilling is also intersecting the known orebody which
is defined in the Inferred Mineral Resource. Example in Figure 6 below is of the New Constitution
zone within the known Mineral Resource. This example highlights a 6.3m zone of banded strongly
sericitic alteration where sulphide mineralisation is contained.
Figure 6: TRDD003 82.8m – 89.8m zone of intense alteration banding with sulphide mineralisation associated with the alteration. 3,4
Darts Chairman, James Chirnside, commented: “Now that we have ramped up operating capacity
by relocating critical equipment and infrastructure to Triumph, we’re really starting to get into the
swing on the drilling front. The first 10 holes have highlighted to us the importance of system
interpretation. The technical team has been reviewing historical core and ore from the nearby open
pit mine to further enhance our understanding.
Several of the key zones intersected to date are exciting, but more importantly, new lodes have been
intersected. We’ve always believed that Triumph has expansion potential along strike and
particularly at the junction of cross cutting ‘corridors’, but now we’re also considering that
mineralisation can just as likely be stacked, adjacent and parallel to the existing known
mineralisation. This has the potential to add considerable mineralisation within a pit envelope
without increasing the waste to ore ratio, improving any future mining economics.”
3
Asp = arsenopyrite, Py = pyrite, Sph = sphalerite, and Cpy = Chalcopyrite
4
Visual estimates of mineralisation presence and abundance contained in this announcement should never be considered a proxy or substitute for
Laboratory analysis. Visual estimates potentially provide no information regarding concentration of economic grades or factors, impurities or
deleterious physical properties relevant to valuation.
5|Page
EXPANSION FOCUS – NORTH AND SOUTH CORRIDOR
Existing drill intercept highlights are shown on Figure 8 for the Southern Mineralised Corridor
including the Super Hans, Big Hans, New Constitution and South Constitution resource blocks.
Existing drill intercept highlights are shown on Figure 7 for the Northern Mineralised Corridor
including the Bald Hill resource block and historic Advance mine area. Both areas highlight strong
geophysical extensions which is shown in the background of Figure 7 and Figure 8 by the high
chargeability (ASX: MBK Nov 2016, MBK Jan 2017) as well as historical and current drilling intersecting
high grade material. These areas will be a focus for Mineral Resource growth as Dart works through
the numerous targets at Triumph.
Figure 7 – Existing drill intercept highlights for the Southern Mineralised Corridor including (east to west) the Super Hans, Big Hans,
New Constitution and South Constitution inferred resource blocks with chargeability (geophysics) maps as the background.
Figure 8 - Existing drill intercept highlights the Northern Mineralised Corridor including the Bald Hill inferred resource block, Bald
Hill East and historic Advance mine area with chargeability (geophysics) maps as the background.
6|Page
NEXT STEPS
At the Triumph Gold Project, Dart intends to;
•
Continue its of diamond drilling programme to expand the existing resources along strike
and at depth
•
Undertake regional exploration, targeting the broader project area;
•
Testing bulk tonnage targets; and
•
Review and identify additional prospective target zones for exploration at Triumph in
addition to existing resource areas.
Please join the discussion on our InvestorHub forum for Investors here:
Approved for release by the Board of Directors.
For more information contact:
James Chirnside
Managing Director
Dart Mining NL
jchirnside@dartmining.com.au
+61 419 605 842
Owen Greenberger
Head of Exploration / Investor Relations
Dart Mining NL
ogreenberger@dartmining.com.au
7|Page
About Dart Mining
In December 2024 Dart Mining (ASX:DTM) completed the acquisition of the Triumph Gold Project, this is Dart’s
first step into an advanced intrusion related gold system project in Queensland. Dart will look to develop a
regional presence in Queensland through advanced stage intrusion related and epithermal gold projects. On
4 March 2025 Dart announced an updated inferred JORC (2012) compliant MRE for Triumph of 2.16Mt @
2.17g/t Au for 150koz gold at a 1g/t Au cut-off (ASX: DTM March 2025).
Dart Mining will continue to evaluate and explore divestment of several historic goldfields in Central Victoria
including the Rushworth Goldfield and continues on a pathway of divestment of out porphyry and lithium
province in Northeast Victoria.
Dart Mining confirms that it is not aware of any new information or data that materially affects the
information included in this, or referenced relevant market announcements and, in the case of estimates of
mineral resources or ore reserves, that all material assumptions and technical parameters underpinning the
estimates continue to apply and have not materially changed
Competent Person’s Statement
The information in this report has been prepared, compiled, and verified by Mr Andrew Dawes, who is a
Member of the Australasian Institute of Mining and Metallurgy and a Member of the Australian Institute of
Geoscientists. Mr Andrew Dawes is employed by AHD Resources and consults to Dart Mining NL. Mr Andrew
Dawes has sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012
Edition of the ‘Australasian Code for Reporting of Mineral Resources. Mr Andrew Dawes consents to the
inclusion in the report of the matters based on his information in the form and context in which it appears.
Dart Mining confirms that it is not aware of any new information or data that materially affects the
information included in this, or referenced relevant market announcements and, in the case of estimates of
mineral resources or ore reserves, that all material assumptions and technical parameters underpinning the
estimates continue to apply and have not materially changed
Forward-Looking Statement
Certain statements contained in this document constitute forward-looking statements. Forward-looking
statements include, but are not limited to, Dart Mining’s current expectations, estimates and projections
about the industry in which Dart Mining operates, and beliefs and assumptions regarding Dart Mining’s future
performance. Such forward-looking statements are based on a number of estimates and assumptions made
by the Company and its consultants in light of experience, current conditions and expectations of future
developments which the Company believes are appropriate in the current circumstances. When used in this
document, words such as; “anticipate”, “could”, “intends”, “estimate”, “potential”, “plan”, “seeks”, “may”,
“should”, and similar expressions are forward-looking statements. Although Dart Mining believes that its
expectations presented in these forward-looking statements are reasonable, such statements are subject to
known and unknown risks, uncertainties and other factors, which may cause the actual results, achievements
and performance of the Company to be materially different from the future results and achievements
expressed or implied by such forward-looking statements. Investors are cautioned that forward-looking
information is no guarantee of future performance and accordingly, investors are cautioned not to place
undue reliance on these forward-looking statements.
8|Page
APPENDIX ONE
DRILL HOLE COLLAR TABLE
Hole ID
Easting (m)
Northing (m)
Elevation (m)
Drill Hole Depth
(m)
TRDD001
334,274.78
7,308,972.63
152.64
32.2
TRDD002A
334,274.78
7,308,972.63
152.64
128.6
TRDD001A
334,293.88
7,308,954.98
155.05
147.8
TRDD002
334,276.83
7,308,974.41
152.64
47.2
TRDD003
TRDD004
334,435.33
334,696.11
7,308,652.59
7,308,656.69
164.10
163.77
185.4
122.3
TRDD005
334,478.88
7,308,863.90
152.74
161.3
TRDD006
TRDD007
334,385.73
334,377.03
7,308,997.86
7,308,717.45
157.78
147.70
209.3
158.3
TRDD008
334,444.63
7,308,625.98
168.73
83.2
TRDD009
334,445.99
7,308,611.21
168.73
170.3
TRDD010
334,303.33
7,308,935.61
151.59
109.0
VISUAL MINERALISATION LOG
Hole ID
From
(m)
To (m)
Width
(m)
Mineral
1
Min 1 %
Mineral
2
TRDD001
17.4
26.2
8.8
FeOx
1.0%
TRDD001
26.2
32.2
6
FeOx
1.0%
TRDD001A
38
38.35
0.35
PY
5.0%
TRDD001A
43.9
47.95
4.05
PY
0.1%
TRDD001A
47.95
48.25
0.3
PY
0.2%
TRDD001A
48.25
52.3
4.05
PY
0.1%
TRDD001A
52.3
52.7
0.4
PY
2.0%
SPH
1.0%
TRDD001A
52.7
55.65
2.95
PY
0.2%
CPY
0.1%
0.0%
TRDD001A
55.65
55.8
0.15
PY
5.0%
ASP
1.0%
0.0%
TRDD001A
55.8
59.5
3.7
PY
0.1%
0.0%
0.0%
TRDD001A
59.5
59.85
0.35
PY
5.0%
0.5%
0.0%
TRDD001A
59.85
62
2.15
PY
1.0%
0.0%
0.0%
Min 2 %
0.0%
PY
1.0%
0.0%
SPH
2.0%
CPY
CPY
0.0%
0.0%
0.0%
0.0%
2.3
PY
5.0%
SPH
0.2%
TRDD001A
71.4
76.6
5.2
PY
1.0%
SPH
0.2%
2
ASP
15.0%
TRDD001A
78.6
82.15
3.55
PY
0.1%
PY
5.0%
0.0%
CPY
ASP
Comments
FeOX on
fractures
FeOX on
fractures and
weakly
disseminated
Py.
0.5%
0.1%
71.4
78.6
ASP
0.0%
69.1
76.6
Min 3 %
0.0%
TRDD001A
TRDD001A
Mineral
3
0.5%
0.2%
Mineralized
Vein with SER
ARG Selvage
Mineralized
Vein
Abundant PY
in SER alt
Intense SER
altered zone
with abundant
sulphides
0.0%
ASP
2.0%
Main Ore zone
Broken QTZ
sulphide Vein
with sheared
upper margin
0.0%
9|Page
TRDD001A
82.15
82.75
0.6
PY
5.0%
0.0%
0.0%
TRDD001A
82.75
137.3
54.55
PY
0.1%
0.0%
0.0%
TRDD001A
137.3
138.5
1.2
PET
5.0%
ASP
1.0%
TRDD002
31.5
31.6
0.1
PY
0.5%
FeOx
0.4%
TRDD002
42
47.2
5.2
PY
0.2%
SPH
0.1%
TRDD002A
0
20.8
20.8
NS
0.0%
TRDD002A
38.4
40.5
2.1
PY
0.3%
TRDD002A
40.5
41
0.5
PY
2.0%
SPH
2.0%
GAL
0.1%
TRDD002A
41
44
3
PY
0.2%
CPY
0.1%
GAL
0.1%
TRDD002A
44
44.5
0.5
PY
2.0%
GAL
0.5%
ASP
0.5%
TRDD002A
50.6
51.1
0.5
PY
1.0%
SPH
0.5%
CPY
0.1%
TRDD002A
60
60.6
0.6
PY
0.2%
PY
0.0%
0.0%
TRDD002A
67
69
2
PY
0.5%
SPH
0.1%
0.0%
TRDD002A
69
70
1
PY
2.0%
SPH
2.0%
TRDD002A
70
77.5
7.5
PY
0.1%
0.0%
0.0%
TRDD002A
92.5
93.9
1.4
PY
0.1%
0.0%
0.0%
SPH
0.0%
CPY
0.0%
0.2%
0.1%
0.0%
0.0%
SPH
0.5%
ASP
96.1
2.2
PY
0.5%
TRDD002A
96.1
119.8
23.7
PY
0.1%
0.0%
0.0%
TRDD002A
119.8
120.7
0.9
PY
5.0%
0.0%
0.0%
TRDD002A
120.7
128.6
7.9
PY
0.1%
0.0%
0.0%
TRDD003
3.6
4.8
1.2
PY
0.5%
ASP
0.1%
0.0%
TRDD003
4.8
25.8
21
PY
0.1%
SPH
0.1%
0.0%
TRDD003
25.8
26.6
0.8
PY
0.5%
CPY
0.1%
0.0%
TRDD003
35.2
36.2
1
PY
0.5%
0.0%
0.0%
49.15
0.85
PY
10.0%
SPH
2.0%
TRDD003
49.15
57.6
8.45
PY
0.5%
SPH
0.1%
TRDD003
57.6
60
2.4
PY
2.0%
SPH
0.5%
TRDD003
71.8
72
0.2
PY
1.0%
TRDD003
76.25
82.8
6.55
PY
0.1%
SPH
CPY
0.5%
93.9
48.3
Precollar no
sample
0.0%
TRDD002A
TRDD003
Abundant PY
with strong
SER alt
Trace py in
Veinlet
Mineralized
Vein with SR
Altered
selvage
Pyrite in
transition
zone
GAL
0.1%
0.5%
Also trace Cpy
trace
sulphides in
veinlet
Trace Py with
sericite
alteration
Mineralized
zone
Also trace
Galena in
Vein. Altered
zone with
parallel
Veinlets with
CHL SER
alteration
Abundant py
in Argilic
alteration
Trace Py and
on fractures
Trace
sulphides in
Veinlets
Mineralized
Vein with
bladed calcite
and strong
SER
0.0%
ASP
0.2%
0.0%
0.0%
0.1%
0.0%
Intensely
altered wall
rock
10 | P a g e
TRDD003
82.8
89.1
6.3
ASP
2.0%
PY
0.5%
TRDD003
97.4
98.9
1.5
PY
0.5%
ASP
0.5%
0.0%
TRDD003
101.1
108.9
7.8
PY
0.1%
0.0%
0.0%
TRDD003
115.5
115.7
0.2
PY
1.0%
ASP
0.5%
0.0%
TRDD003
119
119.25
0.25
PY
0.1%
ASP
0.1%
0.0%
TRDD003
122.4
124.25
1.85
PY
2.0%
ASP
0.5%
0.0%
TRDD003
127.1
130.4
3.3
PY
0.5%
ASP
0.1%
0.0%
TRDD003
133.1
134.4
1.3
PY
0.1%
0.0%
0.0%
TRDD003
141.65
142
0.35
ASP
2.0%
PY
1.0%
CPY
0.5%
TRDD003
147
147.4
0.4
PY
10.0%
ASP
1.0%
GAL
0.5%
TRDD003
155.2
155.3
0.1
PY
1.0%
ASP
1.0%
0.0%
TRDD003
158.55
164.2
5.65
PY
0.2%
ASP
0.1%
0.0%
TRDD003
167.5
167.7
0.2
PO
1.0%
PY
1.0%
0.0%
TRDD003
170.4
170.6
0.2
ASP
1.0%
PY
0.5%
0.0%
TRDD003
180.4
180.7
0.3
PO
0.5%
PY
0.1%
0.0%
TRDD004
11
15.3
4.3
PY
0.5%
SPH
0.3%
TRDD004
19.9
20
0.1
PY
2.0%
TRDD004
23.3
24.8
1.5
PY
1.0%
SPH
CPY
GAL
0.5%
0.0%
0.2%
0.0%
TRDD004
36
38
2
PY
0.3%
0.0%
0.0%
TRDD004
48.5
48.7
0.2
PY
0.5%
0.0%
0.0%
TRDD004
60.4
63
2.6
PY
0.1%
0.0%
0.0%
TRDD004
63
68
5
PY
2.0%
GAL
0.5%
TRDD004
68
77.1
9.1
PY
0.2%
SPH
0.1%
0.0%
0.5%
TRDD004
77.1
86.3
9.2
PY
0.1%
0.0%
0.0%
TRDD004
102.25
102.45
0.2
PY
0.2%
0.0%
0.0%
TRDD005
21.85
22.25
0.4
PY
0.5%
0.0%
0.0%
TRDD005
33.1
38.3
5.2
PY
1.0%
SPH
0.2%
TRDD005
38.3
54.2
15.9
PY
0.1%
PO
0.1%
0.0%
TRDD005
54.2
54.5
0.3
PY
2.0%
ASP
1.0%
0.0%
TRDD005
55.1
55.25
0.15
ASP
5.0%
PY
1.0%
TRDD005
55.25
62.5
7.25
PY
0.1%
TRDD005
62.5
64.45
1.95
PY
0.2%
TRDD005
79.3
85.6
6.3
PY
TRDD005
98.65
99.75
1.1
TRDD005
99.75
105.85
TRDD005
110.15
110.35
GAL
SPH
0.1%
1.0%
0.0%
0.0%
SPH
0.1%
0.0%
0.1%
PO
0.1%
0.0%
ASP
1.0%
PY
0.5%
0.0%
6.1
PY
0.1%
0.0%
0.0%
0.2
PY
0.2%
0.0%
0.0%
ASP
Also Galena
Mineralized
Vein with SER
and Epidote
selvage.
Patch of SER
with Po and
Py
Patch of SER
with Po and
Py
0.1%
0.0%
SPH
Also Spherite
and Galena.
In subparallel
Veins with
laminated
textures
Mineralized
Zone. Also
Asp in Veins.
Shear in lower
portion.
Sulphides in
Vein with SER
selvages
Po in Veinlet
@ 45.35m
Py and asp
with KFs
Also
Sphalerite
Po in veinlet
@ 81.5m
11 | P a g e
TRDD005
116.1
118.35
2.25
ASP
0.5%
SPH
0.2%
TRDD005
148
148.3
0.3
PY
0.2%
SPH
0.1%
0.0%
TRDD006
37.2
49.5
12.3
PY
0.2%
PO
0.1%
0.0%
TRDD006
59
60.2
1.2
PY
1.0%
0.0%
0.0%
TRDD006
65.6
66
0.4
PY
5.0%
0.2%
0.0%
TRDD006
70.85
76.6
5.75
PY
0.1%
0.0%
0.0%
TRDD006
77.8
77.9
0.1
PY
1.0%
CPY
0.2%
0.0%
TRDD006
105
105.2
0.2
PY
1.0%
SPH
0.2%
TRDD006
114.3
114.6
0.3
ASP
15.0%
CPY
5.0%
TRDD006
118.55
118.6
0.05
SPH
2.0%
CPY
0.0%
0.0%
TRDD006
122
127.7
5.7
PY
0.5%
SPH
0.1%
0.0%
TRDD006
132
137
5
PY
5.0%
ASP
0.5%
0.0%
TRDD006
141.4
142.5
1.1
PY
0.0%
0.0%
0.0%
TRDD006
163.3
167.3
4
PY
2.0%
ASP
0.5%
0.0%
TRDD006
175.3
180.5
5.2
PY
0.3%
ASP
0.1%
0.0%
TRDD006
185
185.2
0.2
PY
1.0%
0.0%
0.0%
TRDD006
192
197.5
5.5
PY
0.1%
0.0%
0.0%
TRDD007
9.1
9.6
0.5
PY
0.5%
0.0%
0.0%
TRDD007
13.4
14.45
1.05
PY
0.5%
0.0%
0.0%
TRDD007
40.65
40.8
0.15
PY
0.5%
0.0%
0.0%
TRDD007
50.1
50.35
0.25
PY
10.0%
ASP
1.0%
0.0%
TRDD007
54.2
56
1.8
PY
1.0%
ASP
0.1%
0.0%
TRDD007
64.35
67.25
2.9
PY
2.0%
ASP
1.0%
0.0%
TRDD007
77.75
77.9
0.15
PY
2.0%
SPH
1.0%
0.0%
TRDD007
92.9
93.05
0.15
PY
0.2%
0.0%
0.0%
TRDD007
100.5
104.3
3.8
PY
2.0%
1.0%
0.0%
TRDD007
107.2
107.3
0.1
PY
0.5%
0.0%
0.0%
TRDD007
114.65
115.79
1.14
PY
0.5%
SPH
0.2%
TRDD007
128.85
128.95
0.1
PY
5.0%
SPH
3.0%
TRDD007
139.6
139.95
0.35
PY
2.0%
SPH
1.0%
TRDD007
139.95
142.6
2.65
PY
1.0%
ASP
0.5%
TRDD008
7.1
11
3.9
PY
0.5%
SPH
0.1%
TRDD008
11
11.05
0.05
CPY
1.0%
TRDD008
11.05
14.7
3.65
PY
0.2%
TRDD008
18.2
30.7
12.5
PY
TRDD008
35.15
35.3
0.15
SPH
ASP
GAL
0.1%
0.0%
SPH
GAL
4.0%
0.2%
GAL
0.0%
CPY
0.1%
0.0%
1.0%
PO
0.2%
CPY
0.1%
PY
2.0%
SPH
0.2%
CPY
0.1%
41
41.5
0.5
PO
0.5%
58.45
0.4
PY
2.0%
TRDD008
62
62.3
0.3
PY
0.1%
0.0%
ASP
0.2%
0.0%
Trace Py with
fault
Mineralized
Vein with SER
Mineralized
Zone
Mineralized
Zone
Also minor
Cpy
Mineralized
zone
0.1%
CPY
58.05
Intense SER
alteration
PY in fault
zone
0.2%
0.0%
TRDD008
also Py
Sulphides on
margin of
Dolerite
0.0%
0.0%
TRDD008
Veins in SER
with
Sulphides
Cpy
disseminated
between
crystals along
interpreted
contact of 2
tonalites
0.0%
SPH
0.1%
0.0%
12 | P a g e
TRDD008
71.2
73.3
2.1
PY
0.5%
ASP
0.2%
TRDD008
76.7
76.9
0.2
PY
5.0%
ASP
1.0%
0.0%
TRDD008
78.5
79.55
1.05
PY
0.1%
PO
0.1%
0.0%
TRDD009
3.9
18.5
14.6
PY
0.2%
PO
0.1%
0.0%
TRDD009
66.1
69.2
3.1
PY
1.0%
0.0%
0.0%
ASP
69.2
71.9
2.7
PY
3.0%
TRDD009
71.9
78.35
6.45
PY
0.1%
0.0%
0.0%
TRDD009
89.55
93.9
4.35
PY
0.1%
0.0%
0.0%
TRDD009
99.8
116
16.2
PY
0.1%
0.0%
0.0%
TRDD009
116
119.85
3.85
ASP
3.0%
TRDD009
119.85
126.5
6.65
PY
0.1%
TRDD009
133.8
134.1
0.3
PY
1.0%
TRDD009
137.4
143.25
5.85
PY
0.1%
TRDD009
144.35
149.3
4.95
PY
1.0%
PO
1.0%
SPH
0.2%
TRDD009
155.2
165.45
10.25
PY
0.2%
PO
0.1%
SPH
0.1%
ASP
2.0%
SPH
0.1%
TRDD009
PY
3.0%
SPH
SPH
0.5%
1.0%
0.0%
0.0%
0.2%
0.0%
0.0%
0.0%
Mineralized
Veins with
disseminated
Py. Also in
Venis is Cpy
and Gal.
Mineralized
Veins. Also is
Cpy and Gal.
13 | P a g e
APPENDIX TWO
JORC Code, 2012 Edition – Table 1 report template
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria
JORC Code explanation
Sampling
techniques
• Nature and quality of sampling (eg cut channels, random chips, or
specific specialised industry standard measurement tools appropriate
to the minerals under investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity
and the appropriate calibration of any measurement tools or systems
used.
• Aspects of the determination of mineralisation that are Material to the
Public Report.
• In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘reverse circulation drilling was used to obtain 1
m samples from which 3 kg was pulverised to produce a 30 g charge
for fire assay’). In other cases more explanation may be required,
such as where there is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation types (eg
submarine nodules) may warrant disclosure of detailed information.
• Drill type (eg core, reverse circulation, open-hole hammer, rotary air
blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple
or standard tube, depth of diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by what method, etc).
• Method of recording and assessing core and chip sample recoveries
and results assessed.
• Measures taken to maximise sample recovery and ensure
representative nature of the samples.
• Whether a relationship exists between sample recovery and grade
and whether sample bias may have occurred due to preferential
loss/gain of fine/coarse material.
Drilling
techniques
Drill sample
recovery
Commentary
•
No sampling or results are reported and is not applicable
•
Standard tube HQ diamond drilling was utilised with bottom of
hole core orientation completed every run. An Axis orientation
tool was utilised.
•
Core recoveries for DD was recorded by measuring the total
amount of core between each core block. This was then
compared to the recovery noted on the core block by the driller
and any errors were rectified. The Rock Quality Designation
(RQD) value is calculated by summing the total length of core in
the run composed of pieces of core greater than 10 cm in
length. The recovery and RQD are both converted to a
percentage of the recovery during the data entry phase. At this
14 | P a g e
14 | P a g e
Criteria
Logging
Subsampling
techniques
and sample
preparation
Quality of
assay data
and
laboratory
tests
JORC Code explanation
• Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
studies.
• Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.
• The total length and percentage of the relevant intersections logged.
• If core, whether cut or sawn and whether quarter, half or all core
taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.
• For all sample types, the nature, quality and appropriateness of the
sample preparation technique.
• Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
• Measures taken to ensure that the sampling is representative of the in
situ material collected, including for instance results for field
duplicate/second-half sampling.
• Whether sample sizes are appropriate to the grain size of the material
being sampled.
• The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is considered
partial or total.
• For geophysical tools, spectrometers, handheld XRF instruments, etc,
the parameters used in determining the analysis including instrument
make and model, reading times, calibrations factors applied and their
derivation, etc.
• Nature of quality control procedures adopted (eg standards, blanks,
Commentary
•
time, further geotechnical information is recorded such as
Longest Unbroken Piece (LUP) and Rock Strength. The LUP is
recorded as the longest piece of core within each block-to-block
interval. The Rock Strength class is recorded as an average, also
between core block to core block. Fracture count involved
counting individual fractures within a drill run. If the core was
crushed and fractures were too numerous to accurately count,
it was given the designation “999” which indicated a highly
fractured zone.
The drill core has been geologically and geotechnically logged to
a level to support appropriate mineral resource estimation,
mining studies and metallurgical studies. Core is logged both
qualitatively and quantitatively. Core and photography is
available.
•
No results from sampling have been reported in this
announcement.
•
No results from sampling have been reported in this
announcement.
15 | P a g e
Criteria
JORC Code explanation
Commentary
duplicates, external laboratory checks) and whether acceptable levels
of accuracy (ie lack of bias) and precision have been established.
Verification
of sampling
and
assaying
Location of
data points
•
•
•
•
•
•
•
The verification of significant intersections by either independent
or alternative company personnel.
The use of twinned holes.
Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.
Discuss any adjustment to assay data.
Accuracy and quality of surveys used to locate drill holes (collar
and down-hole surveys), trenches, mine workings and other
locations used in Mineral Resource estimation.
Specification of the grid system used.
Quality and adequacy of topographic control.
•
No results from sampling have been reported in this
announcement.
•
The location of drill hole collars were confirmed with a Trimble
DA2 receiver and Catalyst 0.3m Subscription set to MGA94 Grid
Datum (Zone 56)
Accuracy is variable but is expected to be 0.3m
During the mapping and Collar pickup process with constant
visual quality assessment conducted, the receiver maintained
an accuracy level <0.4m.
Down hole, multi-shot surveys were taken at 15m then a
nominal 30 m interval where possible using a Trueshot survey
tool. A 3m multi-shot survey was conducted at end of hole.
No results from sampling have been reported in this
announcement.
•
•
•